Summary of investment and construction of the 500kV circuit 3 line project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen)

On December 8, the Government held a conference to summarize the investment and construction of the 500kV circuit 3 line project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) (500kV circuit 3 line project). The conference was held in an online format, connecting from the bridge point of Vietnam Electricity Group (EVN) to the bridge points of the 9 provinces where the project passes through....

On December 8, the Government held a conference to summarize the investment and construction of the 500kV circuit 3 line project from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) (500kV circuit 3 line project). The conference was held in an online format, connecting from the bridge point of Vietnam Electricity Group (EVN) to the bridge points of the 9 provinces where the project passes through....

Comrade Pham Minh Chinh, Member of the Politburo, Prime Minister chaired the conference. Attending the conference at Hung Yen bridge were comrades: Nguyen Huu Nghia, Member of the Party Central Committee, Secretary of the Provincial Party Committee; Lieutenant General Nguyen Quang Ngoc, Member of the Party Central Committee, Commander of Military Region 3; Tran Quoc Van, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee; Colonel Nguyen Thanh Truong, Member of the Provincial Party Standing Committee, Director of the Provincial Police.

 Các đại biểu dự hội nghị tại điểm cầu Hưng Yên 

 Delegates attending the conference at Hung Yen bridge

The 500kV circuit 3 line project was assigned by EVN to the National Power Transmission Corporation (EVNNPT) as the investor. The project includes 4 component projects: Quang Trach - Quynh Luu 500kV line; 500kV Quynh Luu - Thanh Hoa line; 500kV line of Nam Dinh I thermal power plant - Thanh Hoa; 500kV line of Nam Dinh I - Pho Noi thermal power plant. The project has a total length of about 519km with 1,177 column foundation positions, total investment of about 22,300 billion VND. The project passes through 211 communes and wards of 43 districts and towns in 9 provinces including Quang Binh, Ha Tinh, Nghe An, Thanh Hoa, Ninh Binh, Nam Dinh, Thai Binh, Hai Duong, Hung Yen. This project plays a particularly important role in improving the stable reserve capacity of the power system, increasing power supply to the North in 2024 and the following years, contributing to ensuring national energy security. family.
Under the drastic direction of the Prime Minister, the Government, the attention and support of ministries, departments, branches, localities and people, EVN and EVNNPT have made efforts to complete the project after more than 6 months. Construction and energization of the project according to the assigned schedule.
 
The investment preparation work of the project only took nearly 5 months from the time of deciding to implement it.  This is a record short time, while projects of similar scale take 2-3 years. In contractor selection, with a total of 226 component projects, EVNNPT has gathered all qualified human resources, organized centralized bid evaluation, worked day and night, with no days off. The result was completed in about 60 days. Regarding site clearance compensation, the project has a large amount of land clearance compensation, with a total area of ​​land recovery of about 183 hectares. With the direction of the Prime Minister, ministries, the participation of the provinces and the support of the people of 9 provinces, by March 8, 2024, 1,177/1,177 positions were completed. column foundation, on June 17, 2024, the corridor for 513/513 anchorages was completely handed over to the investor. Fast site clearance progress is one of the important factors contributing to the success of the project...
 
At the conference, delegates discussed and clarified a number of issues in implementing the 500kV Circuit 3 Line project such as: Administration, direction and coordination to remove difficulties during project implementation; conversion of forest land use purposes to serve project implementation; Compensation and site clearance work for the project; Mobilize forces to participate in supporting project implementation...
 
Speaking at the conference, Prime Minister Pham Minh Chinh praised the efforts of EVN and all levels and sectors, as well as the consensus and support of the people in implementing the 500kV Circuit 3 Line project. The Prime Minister affirmed that, with the drastic leadership and direction of the Government, the determination and efforts of the entire political system, the 500kV Circuit 3 Line project is a project with rapid construction progress show solidarity and unity of the entire political system under the leadership of the Party. The project put into operation contributes to ensuring national energy security; strengthen trust with foreign investors and partners; Expressing the aspirations, beliefs, and values ​​of Vietnamese people...
 
The Prime Minister requested that in the coming time, EVN and EVNNPT coordinate well to organize and operate the 500kV circuit 3 line project together with the national power system safely and achieve the highest efficiency; At the same time, continue to invest in developing power sources and grid systems, ensuring adequate and steady supply of electricity demand for socio-economic development; Actively participate in ensuring social security and stabilizing people's lives...

Các tin khác

Tin mới nhất

Xem nhiều nhất

Fanpage

Bình chọn

Đánh giá của bạn về Trang Thông tin điện tử tổng hợp Đối ngoại Hưng Yên
1 người đã bình chọn

Thống kê truy cập

  • Hôm nay:
  • Hôm qua:
  • Tuần này:
  • Tháng này:
  • Năm nay: