Reviewing the progress of implementation of the Ring Road 4 Construction Investment Project - Hanoi Capital Region

On December 12, at the Hanoi People's Committee Headquarters, the Steering Committee for the Implementation of Ring Road 4 Construction Investment Project - Hanoi Capital Region (Steering Committee) organized a conference to review progress. progress, implementation situation and removal of difficulties and obstacles during the implementation of the Ring Road 4 Construction Investment Project - Hanoi Capital Region (Project)....

On December 12, at the Hanoi People's Committee Headquarters, the Steering Committee for the Implementation of Ring Road 4 Construction Investment Project - Hanoi Capital Region (Steering Committee) organized a conference to review progress. progress, implementation situation and removal of difficulties and obstacles during the implementation of the Ring Road 4 Construction Investment Project - Hanoi Capital Region (Project)....

Attending the conference were comrades: Bui Thi Minh Hoai, Politburo member, Secretary of the Hanoi Party Committee, Head of the Steering Committee; Nguyen Huu Nghia, Member of the Party Central Committee, Secretary of Hung Yen Provincial Party Committee, Deputy Head of the Steering Committee; Tran Sy Thanh, Member of the Party Central Committee, Chairman of the Hanoi People's Committee, Deputy Head of the Steering Committee...

Toàn cảnh hội nghị

Overview of the conference
According to a report at the conference, the project has a total length of 112.8km, passing through Hanoi city and the provinces of Hung Yen and Bac Ninh. The project is implemented in 7 component projects, operated independently, including: 3 component projects implementing compensation and resettlement support in the area of ​​each province and city (component projects 1.1, 1.2 and 1.3); 3 component projects invest in parallel road construction in each province and city (component projects 2.1, 2.2 and 2.3) and component project 3 invests in building a highway system.
 
To date, Hanoi city has approved and recovered 786.2 hectares of land, reaching 98.44%; moved 10,281 graves, reaching 99.36%; received 776.82 hectares of land, equivalent to 48.35km, reaching 91.7%. For moving high voltage electricity, 4/16 intersection points have been completed, 37/39 column foundation positions have been handed over, and construction of 33/39 high voltage pole foundations has been completed. Construction output of component 2.1 project reached 43.04% of contract value and 100% of the 2024 plan.
In Hung Yen province, land clearance for agricultural land, public land, and business land has basically been completed. To date, Hung Yen province has recovered and handed over 215 hectares of land, reaching 95.1%; moved 4,193 graves, reaching 99.5%. Construction of 29/33 electric pole foundations is being organized to serve the relocation of 110kV, 220kV, 500kV electrical systems. The construction output of component 2.2 project reached 28% of the contract value and 97.11% of the approved schedule.
 
In Bac Ninh province, the plan has been approved and 363.84 hectares of land recovered, reaching 97.28%; Basically completed moving the grave. Moved a total of 37 high voltage pole positions of 110kV, 220kV, 500kV and completed construction of 18/32 pole foundation positions with the site handed over. Construction output of component 2.3 project reached 13.6% of the planned value.
 
Regarding disbursement and payment situation, for Hanoi city, the capital plan has allocated more than 14 trillion VND, disbursed 71.81%. For Hung Yen province, the capital plan has allocated more than 5.2 trillion VND, disbursed 56.69%. For Bac Ninh province, the capital plan has allocated more than 3.6 trillion VND, disbursed 60.97%.
At the conference, delegates focused on discussing solutions to speed up project implementation.
Speaking at the conference, Secretary of the Hung Yen Provincial Party Committee Nguyen Huu Nghia said that Hung Yen province is trying to implement solutions to speed up the implementation of the Project and has achieved many important results. Comrade Secretary of the Provincial Party Committee Nguyen Huu Nghia emphasized: Hung Yen Province is implementing the Project according to the specific order and mechanism approved by the National Assembly in Resolution No. 56/2022/QH15 dated June 16, 2022. basically meet the required progress. Provincial Party Secretary Nguyen Huu Nghia requested the Steering Committee to report to competent authorities to adjust and increase the funding for component project 1.2 in Hung Yen province by about 600 billion VND. At the same time, the Steering Committee, based on the opinions and recommendations of the localities on difficulties and problems during project implementation, reports to the Government and ministries and branches to have a solution plan in time. earliest…

Đồng chí Bùi Thị Minh Hoài, Ủy viên Bộ Chính trị, Bí thư Thành ủy Hà Nội, Trưởng Ban chỉ đạo phát biểu tại hội nghị

Comrade Bui Thi Minh Hoai, Politburo member, Secretary of the Hanoi Party Committee, Head of the Steering Committee spoke at the conference
Speaking at the conclusion of the conference, comrade Bui Thi Minh Hoai, Politburo member, Secretary of the Hanoi Party Committee, Head of the Steering Committee acknowledged the efforts and flexibility of localities and their participation in overcoming difficulties. difficulties, obstacles, support and guidance from ministries and branches in project implementation. However, the implementation process still has difficulties and obstacles affecting the project progress. Comrade Secretary of the Hanoi Party Committee Bui Thi Minh Hoai emphasized: The investment project to build Ring Road 4 - Hanoi Capital Region is a national key project, with important significance for linking the region and promoting socio-economic development. Therefore, localities focus on overcoming difficulties and obstacles to ensure project implementation progress according to the direction of the National Assembly, the Government and the Prime Minister. Regarding suggestions and recommendations from localities, the Steering Committee will synthesize reports and propose to the National Assembly, the Government and ministries and branches to resolve them as soon as possible. In the coming time, localities need to mobilize the combined strength of the entire political system to simultaneously deploy tasks to shorten the time to carry out tasks, especially removing difficulties. , problems, speed up site clearance progress...

Các tin khác

Tin mới nhất

Xem nhiều nhất

Fanpage

Bình chọn

Đánh giá của bạn về Trang Thông tin điện tử tổng hợp Đối ngoại Hưng Yên
1 người đã bình chọn

Thống kê truy cập

  • Hôm nay:
  • Hôm qua:
  • Tuần này:
  • Tháng này:
  • Năm nay: